When you buy an under-construction flat from abroad, two documents carry most of the protection RERA gives you: the project's separate bank account (often called the "70% escrow") and the registered agreement for sale. Both are easy to mention in a brochure and easy to misunderstand. This post sets out what the Real Estate (Regulation and Development) Act, 2016 actually says, how two states put it into practice, and the questions to settle before you sign or send a large payment.
Please read this first. Holdengard is not a broker or adviser. It is not RERA-registered and holds no real-estate licence at present. It lists no properties, takes no fee on any transaction and promises no return. This page is general information, not legal, tax or investment advice. Verify every point with a licensed local lawyer and, for money moving from abroad, your chartered accountant and authorised dealer bank.
What section 4(2)(l)(D) actually says
When a promoter applies to register a project, section 4(2)(l) requires a declaration, supported by an affidavit. Sub-clause (D) of that declaration says that seventy per cent of the amounts realised for the project from the allottees, from time to time, shall be deposited in a separate account maintained in a scheduled bank, to cover the cost of construction and the land cost, and shall be used only for that purpose.
The same clause adds three provisos:
- The promoter withdraws from the separate account in proportion to the percentage of completion of the project.
- Each withdrawal is allowed only after an engineer, an architect and a chartered accountant in practice certify that it is in proportion to the completion.
- The promoter must get the accounts audited within six months after the end of every financial year by a chartered accountant in practice, and the audit must verify that money collected for the project was used for that project and that withdrawals matched the completion percentage.
A "scheduled bank" here means a bank in the Second Schedule to the Reserve Bank of India Act, 1934.
Two things the clause does not say. It is not a third-party escrow in the everyday sense: the account belongs to the promoter, and the control is the certification and audit trail. And it does not guarantee completion. It reduces the risk that your money is diverted to another project; it cannot make an under-funded project solvent.
How states run the separate account: two examples
The Act leaves the detail to state rules and regulators, so the paperwork differs by state. Two examples from official texts:
Maharashtra. Rule 5 of the Maharashtra RERA registration rules, 2017 requires three certificates to be submitted to the bank operating the separate account for every withdrawal until the occupancy certificate: the project architect certifying the percentage of completion of each building or wing, the engineer certifying the actual construction cost incurred, and a practising chartered accountant certifying the construction and land cost incurred and its proportion to the total estimated cost. That proportion multiplied by the total estimated cost sets the maximum amount that can be withdrawn. For ongoing projects, the same rule says that if estimated receivables are less than the estimated cost of completion, 100% of the amounts to be realised must go into the separate account. MahaRERA publishes the standard formats as Form 1 (architect), Form 2 (engineer), Form 3 (CA certificate for withdrawal) and Form 5 (annual report on withdrawals from the designated account), and asks promoters to declare at registration that the separate account carries no encumbrance or escrow in favour of anyone else (MahaRERA Order No. 34).
Haryana. The Haryana RERA Rules, 2017 repeat the 70% condition in the conditions of registration, and rule 8(1) says the agreement for sale shall be as per Annexure A, the state's model agreement.
| What to check | Where it comes from | What a clean answer looks like |
|---|---|---|
| Separate account exists for this project | Section 4(2)(l)(D) | Account details on the project's RERA registration page, in a scheduled bank, in the project's name |
| Withdrawals are certified | Section 4(2)(l)(D) provisos; Maharashtra rule 5 | Architect, engineer and CA certificates uploaded on the state portal (Forms 1, 2 and 3 in Maharashtra) |
| Annual audit is filed | Section 4(2)(l)(D), third proviso | A CA-certified annual statement within six months of the financial year end (Form 5 in Maharashtra) |
| Construction status matches collections | Section 11(1)(e) quarterly updates | The portal's quarterly progress roughly tracks the stage-wise payments being demanded |
| No other lien on the account | MahaRERA Order No. 34 declaration | A declaration that the separate account is free of encumbrance or escrow to another lender |
Before you sign: six builder agreement checks
1. No large advance before a registered agreement. Section 13(1) bars a promoter from accepting more than ten per cent of the cost as an advance or application fee without first entering into a written agreement for sale and registering it. If you are asked for more on the strength of a booking form, stop.
2. The agreement is in the state's prescribed form. Section 13(2) says the agreement shall be in the form prescribed by the state, and shall specify construction details, specifications, internal and external development works, the dates and manner of payment, the possession date, and the interest rates payable by each side on default. Maharashtra rule 10 points to the model form at Annexure A and allows changes only if they still conform to the Act. MahaRERA also asks promoters to upload a deviation report against the model agreement (Order No. 35). Ask for that deviation sheet and read every line of it.
3. A real possession date, and the same interest rate both ways. Section 18 gives you the right, if possession is not given as agreed, to withdraw and get your money back with interest and compensation, or to stay and receive interest for every month of delay. In Haryana, rule 15 fixes the rate payable by either side at the State Bank of India's highest marginal cost of lending rate plus two per cent, and rule 16 sets 90 days for refunds once due. Check that your draft does not quietly use a lower rate for the builder than for you.
4. Payment stages tied to construction, not to the calendar. Because withdrawals are meant to follow completion, a payment plan that demands most of the price long before the structure is up deserves questions. Compare each stage with the quarterly status the promoter must post under section 11(1).
5. No changes to the plan without your consent. Section 14(2) bars additions or alterations to the sanctioned plans, specifications and fittings of your unit without your previous consent, and changes to the building or common areas without the written consent of at least two-thirds of the allottees. A clause letting the builder "revise plans at its discretion" conflicts with this.
6. Defect liability for five years. Under section 14(3), structural or workmanship defects brought to the promoter's notice within five years of possession must be rectified free of charge within thirty days. Check the agreement does not shorten this.
For the money side, remember that the price is quoted on carpet area (section 2(k)); see carpet area vs super area. Before possession, read occupancy certificate vs completion certificate: section 19(10) expects you to take possession within two months of the occupancy certificate.
The NRI angle: signing from abroad
Most NRIs sign through a relative or agent under a power of attorney. That is exactly when a non-standard clause slips through. Send your attorney the deviation sheet and the six checks above, and read our note on NRI power of attorney safeguards. Pay only from the routes your bank confirms are allowed for you; our NRE vs NRO account guide explains the usual options. If the flat is an investment, run the numbers on our free rental yield and ROI calculator before you commit, using your own rent and cost assumptions rather than a brochure's.
Try it with your own numbers
Open the RERA checklist
Work through registration, carpet area, the separate account and the agreement for your project, step by step.
Open the RERA checklistSources checked
The Real Estate (Regulation and Development) Act, 2016 (India Code text): sections 2(k), 4(2)(l)(D), 11, 13, 14, 18 and 19. Maharashtra Real Estate (Regulation and Development) (Registration of real estate projects, Registration of real estate agents, rates of interest and disclosures on website) Rules, 2017: rules 5 and 10. MahaRERA forms page (Forms 1, 2, 3 and 5; proforma of agreement for sale dated 4 September 2024) and MahaRERA guide for promoter registration (Orders No. 34 and 35). Haryana Real Estate (Regulation and Development) Rules, 2017: rules 8, 15 and 16 and the conditions of registration. All checked on 19 November 2026.
Frequently asked questions
Is the RERA 70% account an escrow controlled by a bank?
Not in the usual sense. Section 4(2)(l)(D) requires 70% of the amounts realised from allottees to be kept in a separate account in a scheduled bank and used only for construction and land cost. Withdrawals need certificates from an engineer, an architect and a practising chartered accountant, and the accounts must be audited every year. The control comes from that certification and audit, not from a third party holding the money.
Can a builder withdraw all the money in the separate account at once?
No. Withdrawals must be in proportion to the percentage of completion of the project. In Maharashtra, the CA certificate fixes the maximum withdrawal as the total estimated cost multiplied by the proportion of cost already incurred, and fresh certificates are needed until the occupancy certificate. On the completion certificate, the remaining balance can be withdrawn.
How much can I pay before the agreement for sale is registered?
Not more than ten per cent of the cost of the apartment, plot or building, under section 13(1) of the RERA Act. Above that, the promoter must first sign and register a written agreement for sale with you.
Can the builder change the agreement from the state model form?
States allow some changes as long as the agreement still conforms to the Act and rules. Maharashtra rule 10 says so, and MahaRERA asks promoters to upload a deviation report showing every change from the model agreement. Ask for it and have your lawyer review each deviation.
Does RERA guarantee my flat will be completed?
No. RERA requires disclosures, the separate account, certified withdrawals, an annual audit, and gives you refund, interest and compensation rights under section 18 if possession is not given as agreed. It does not guarantee completion or any return, so check the project's portal record, progress and paperwork yourself.